Do I need a permit or HOA approval for a driveway, patio or pavers?
Often both, and they are separate. A city or county permit covers the building and zoning rules, while an HOA or architectural review committee covers appearance under your community's documents. A permit never replaces HOA approval, and HOA approval never replaces a permit. Where a permit is required, we prepare the paperwork and the fee is in your written quote.
The right answer depends on your address, and many Central Florida addresses sit under a different office than the mailing city suggests. This guide gives the statewide rules first, then what the official sources say for the areas we serve, then a checklist for HOA applications. Rules change, so confirm any detail with the office before you build.
What are the statewide rules in 2026?
Florida's HB 803 took effect July 1, 2026. It says local governments may not require a building permit for work valued under $7,500 on a single-family lot, except electrical, plumbing, structural, mechanical or gas work (Florida Building Commission summary). It also bars an HOA from requiring a permit before the association reviews your plans. There is no statewide rule that pavers or patios never need a permit.
- The $7,500 exemption is narrow and local. Kissimmee says it still requires a written exemption request and always requires a permit for work valued at $7,500 or more or in a flood zone (city notice). Winter Garden requires its exemption application to be approved before any work begins (city guide).
- Driveways may be treated differently. Boynton Beach, for example, says driveways still need a permit because its driveway rule comes from its zoning code (city page). Ask your city whether the exemption reaches driveways.
- Exempt does not mean unregulated. The Florida Building Code's exemptions do not authorize work that violates the code, and each jurisdiction keeps its own list.
- HOA review can start first. Under the HB 803 change to s. 720.3035, an HOA cannot make a government permit a condition of reviewing your application.
Most driveways run well above $7,500 anyway. A typical paver driveway is about $8,000–$22,000 (see our paver cost guide) and a 600 sq ft concrete driveway about $6,000–$7,800 (see our concrete cost guide), so check the rules for your address instead of assuming an exemption.
Do I have to call 811 before digging?
Yes. Florida law requires an excavator to notify the one-call system at least two full business days before digging (s. 556.105, F.S.). Sunshine 811 says to call for every digging project, large or small, and that the day you request the ticket, weekends and holidays are not counted (Sunshine 811 homeowner FAQ). Locate information is valid for 30 calendar days.
We request the utility locate before anything is dug, as part of our standard process. If a start date slips past 30 days, the locate has to be renewed, which is one reason schedules move. Our process page lists the steps in order.
Who issues the permit, and what do the local sources say?
It depends on where the property is. Incorporated cities such as Ocoee, Winter Garden, Orlando, Kissimmee, Apopka, Clermont and Davenport run their own offices. Dr. Phillips, Celebration and Four Corners are unincorporated, so a county office handles them. Lake Nona is inside the City of Orlando. The table summarizes what the official pages say and links each source.
| Area | Who issues permits | What the official sources say about driveways, aprons and pavers |
|---|---|---|
| Ocoee | City of Ocoee (online permit portal); right-of-way work through Public Works | Permit required for a concrete slab, patio, driveway or pavers, with a site plan; no private-property exemption is stated (city FAQ). A right-of-way utilization permit covers driveways and pavement in the public right-of-way (Public Works). |
| Winter Garden | City Building Division; Horizon West is Orange County | Pavers, concrete and driveways are submitted as electronic zoning permits, and a pre-approval may be required (city page). Paver driveways get an in-progress inspection and a final inspection (city guide). The city says its approval does not override HOA covenants (city FAQ). |
| Orlando | City Permitting Services | An Engineering Permit covers installing pavers or concrete and expanding a driveway. The driveway apron is the area between street and sidewalk, it must match the driveway width, and pavers on it need a notarized Paver Agreement (residential guide; permit types). |
| Kissimmee | City Engineering Division; unincorporated Osceola County for some Kissimmee addresses | Driveway and sidewalk work is requested through the city portal, with at least two business days allowed just to route the plans (city page). The city also says single paver blocks under each tire are not allowed as a driveway surface (code enforcement guide). |
| Windermere | Town of Windermere; building permits are contracted out and right-of-way goes through Town Public Works | Driveway work in the right-of-way needs the town's application, with an application fee, an inspection fee and pre-pour and final inspections. Conditions include a site plan from an engineer or surveyor, no driveway within 5 feet of a side property line, and paver aprons built to FDOT standards (town form; permits page). |
| Apopka | City Building Safety; Engineering Division for right-of-way | The city lists a driveway inspection fee (fee page). We did not find an official statement on whether a private patio needs a building permit, so ask Building Safety (city page). |
| Clermont | City Building Services Division | The city's FAQ says almost everything may need a permit (Building Services). Its fee schedule lists a residential zoning clearance (fee schedule). Ask whether a zoning approval applies to your driveway. |
| Davenport | City Building & Planning Department | Sidewalks and driveway aprons may not include pavers unless the HOA allows it or the building official approves (city land development rules). We did not find a Davenport driveway right-of-way page, so ask the department (city page). |
| Lake Nona | City of Orlando | Lake Nona is inside the City of Orlando, so Orlando's Engineering Permit and apron rules apply (city page). Neighborhood design rules vary and sit with your community. |
| Dr. Phillips | Orange County (unincorporated) | The county says that anytime you pour concrete or place pavers a permit is required, and pavers need a zoning permit only (county page). Work in the right-of-way is tied to a recorded use agreement that makes the owner responsible for maintenance (agreement). |
| Four Corners | Whichever county the parcel is in: Lake, Orange, Osceola or Polk | Lake County exempts some driveways and sidewalks near grade (Lake County list); Orange requires a permit (Orange County); Osceola lists a right-of-way fee plus a charge per curb cut and says HOA or private-easement land needs separate approval (fee schedule). We did not find Polk's rule, so ask the county. |
| Celebration | Osceola County (unincorporated); the community's own architectural review committee | Osceola has a driveway permit application with a checkbox for pavers (application). The community requires an architectural application for exterior changes (design guidelines). |
"Not found" means we could not locate an official statement, not that no rule exists. Phone the office or use its portal before you build. Our service areas page shows which area your address is closest to.
What is a driveway apron, and why does the right-of-way matter?
The apron is the part of the driveway between the street and the sidewalk, and it usually sits in the public right-of-way. Because the public owns that strip, work there is often reviewed separately from work on your own lot. Orlando defines the apron this way and says it must match the driveway width (residential guide).
- Different surface rules. Orlando needs a notarized Paver Agreement for pavers on the apron. Windermere sets its own standards for paver aprons. Davenport allows pavers on aprons only with HOA or building-official approval.
- The owner often keeps the maintenance duty. Orange County's homeowner use agreement makes the homeowner responsible for perpetual maintenance of improvements in the right-of-way (agreement).
- Sidewalks may be protected. Celebration's guideline says the sidewalk parallel to the street may not be altered, and a new paver walkway must be even with it (guideline).
- Utilities and drainage. Winter Garden says soil, stone and pavers may not be stored in the street, sidewalk or drainage swale, and swales must be restored (city guide).
If your driveway layout changes, for example by widening it, read our driveway extension guide too, since extra paved area can also change the impervious-area calculation some offices ask for.
What should I submit to my HOA's architectural review committee?
Most committees want a completed application, a site plan, product spec sheets, color samples or photos, a layout and edge detail, a certificate of insurance and a schedule. Your community's guidelines are the authority, so start by reading them. We prepare the packet for HOA communities, so you only need to send us your guidelines and application form.
- The application form from your management company or the community website, signed by the owner.
- A site plan or survey that marks the driveway, walkway or patio, and its distance from property lines.
- Product spec sheets for the paver or concrete finish, including the manufacturer, series, size and thickness.
- Color samples or photos, as many committees limit colors to an approved palette.
- Layout and pattern drawing showing the field pattern, borders and any soldier course.
- Edge detail: the edge restraint, and how the new surface meets the lawn, the street, the sidewalk and the house.
- A certificate of insurance. Ours covers general liability and workers' compensation and is available on request.
- The schedule: the proposed start date and how long the work is expected to take, with access and staging notes.
Celebration's driveway guideline shows what one community asks for: a scaled survey or plot plan, an impervious-area worksheet and, if the surface is not concrete, a color brochure or physical sample (guideline). Other communities ask for different items, so use your own form. For help choosing a product that is likely to fit a palette, see our best pavers guide.
In what order do the steps go?
A workable order is: read your HOA documents, get the estimate and drawings, submit to the HOA, confirm the permit rule with your city or county, apply for the permit if one is required, request the 811 locate, then schedule the work. Because the HOA cannot require a permit first, you can submit to both at the same time.
- Read the covenants and architectural guidelines, and note anything about materials, colors and impervious limits.
- Get a written estimate that names the product, pattern and edge detail.
- Send the HOA packet and keep proof of the date you submitted it.
- Check the permit rule for your address, including any right-of-way or apron agreement.
- File the permit if one is needed. We prepare the paperwork, and the fee appears in the written quote.
- Get the HOA decision in writing, and the permit if one applies.
- Request the 811 locate, then schedule the start.
How long does approval take?
We cannot promise a number, because each HOA and each permit office sets its own review period. Your community's governing documents usually say how long the committee has to respond, so ask for that period in writing when you submit. Kissimmee asks applicants to allow at least two business days only to route driveway plans for review, which is a routing step and not the full approval.
Three things shorten the wait: a complete packet, product details that match the guidelines, and a quick reply to any question from the reviewer. Incomplete packets are the usual reason reviews stall. We schedule the work after the approvals are in hand, so a longer review simply moves the start date.
What can go wrong if work starts without approval?
An HOA can demand changes or removal at the owner's expense and can pursue fines under its documents. A city or county can require correction of unpermitted work, and the issue can come up again when you sell the home. These outcomes depend on your community and jurisdiction, so treat this as general information, not legal advice.
- Having to remove or redo a finished surface costs far more than the approval process.
- A city permit does not allow you to break HOA covenants, as Winter Garden's FAQ states, so one approval is not enough.
- Right-of-way work without the right agreement can leave you with a repair bill for a public strip.
- If a buyer's inspector finds unpermitted work, it can slow a sale.
A free written estimate from us lists the permit and HOA steps we will handle for your address. Call (689) 356-6292 or use our contact page.